1. Wall preparation
Ensure the load-bearing wall is structurally sound, clean, and ready for installation.
Mark fixing points according to the facade layout.
2. Installation of brackets
Fix vertical brackets to the wall using appropriate anchors.
Adjust bracket depth to accommodate insulation thickness and ventilation gap.
3. Thermal insulation installation
Install insulation boards (e.g. mineral wool) between brackets.
Secure insulation mechanically if required and ensure continuous coverage.
4. Installation of vertical profiles
Attach vertical aluminium profiles to the brackets.
Check alignment and create a continuous load-bearing framework.
5. Ventilation gap setup
Ensure a continuous air cavity between insulation and cladding panels.
Maintain required spacing for proper airflow and moisture regulation.
6. Mounting of horizontal rails
Fix horizontal carrier rails onto the vertical profiles.
Align them according to panel dimensions and fixing system requirements.
7. Installation of concealed fixing system
Mount clips or anchors onto the rails based on engineering specifications.
Ensure precise positioning for load transfer and panel stability.
8. Panel installation
Install UHPC panels by engaging them into the concealed fastening system.
No visible fixings remain on the facade surface.
9. Joint alignment and adjustment
Align panels to achieve consistent joints and clean facade lines.
Verify tolerances and adjust where necessary.
10. Final inspection
Check all connections, ventilation paths, and panel alignment.
Ensure compliance with project specifications and safety standards.
1. Substructure preparation
Install and align the supporting substructure (aluminium or steel) according to project specifications.
Ensure all profiles are levelled and fixed to the load-bearing wall.
2. Installation of horizontal rails
Mount horizontal carrier rails onto the substructure.
Check spacing and alignment to match panel dimensions and load requirements.
3. Fixing system placement
Install the concealed fastening system (clips/anchors) onto the rails.
Position them according to the panel layout and engineering calculations.
4. Panel preparation
Prepare UHPC panels with pre-installed anchors or slots (factory-made).
Inspect panels for any transport damage before installation.
5. Panel mounting
Place panels onto the concealed fixing system.
Secure them by engaging anchors/clips into the rails without visible fasteners.
6. Joint alignment
Adjust panels to achieve consistent joint width and precise alignment.
Ensure a clean, seamless facade appearance.
7. Final inspection
Check fixation points, panel stability, and alignment.
Verify ventilation gaps and compliance with installation guidelines.